Construction work will begin Tuesday 24 June around Centennial Park area to install concrete islands and road line marking. The roads to be marked are: Te Kūiti Road, Park Street, William Street and Ngarongo Road. We ask kindly that this area be kept clear of vehicles and residents do not park on the road for the next couple of days. Thank you for your understanding and cooperation.

Slip on Te Waitere Road – please drive safe

Council is aware of a significant slip on Te Waitere Road. Currently the road is down to one lane with priority give way traffic control in place. Given there is poor weather forecast towards the end of the week, we encourage those needing to pass through this site to be vigilant and drive safely and to the conditions.

Work to begin on View Terrace, Piopio

10 Jan 2023, 3:38 PM

Construction works to fix the major slip on View Terrace in Piopio will start Monday 16 January.

View Terrace was one of several local roads severely impacted by Cyclone Dovi in February 2022, causing extensive flooding and slips, and resulting in millions of dollars worth of repair work.

General Manager Infrastructure Services, Shyamal Ram says while the cyclone wreaked havoc on much of the district, View Terrace was severely impacted and subsequently classified as needing urgent repair.

A plan was agreed in August 2022 to construct a Mechanically Stabilised Earth (MSE) Wall.

“An MSE Wall is the recommended option based on price, disturbance to surrounding properties, and size of the slip. An MSE wall comprises layers of soil or rock sandwiched between artificial reinforcement, usually geogrids and geotextiles.”

Interim measures have been in place during the winter months when the ground is at its wettest, and work will start when the soil has had time to dry.

Inframax Construction Ltd has been awarded the contract, with the majority of funding for the repair coming from Waka Kotahi NZTA.

Further works on other storm-affected roads will also be completed this summer, including Te Anga Road, Fullerton Road, Oparure Road, Mangaotaki Road, Taumatamaire Road and Te Waitere Road.

Kopaki Road, Taumatatotara West Road and Mangatoa Road will be completed later in the year.