Road works - Centennial Park area

Construction work will begin Tuesday 24 June around Centennial Park area to install concrete islands and road line marking. The roads to be marked are: Te Kūiti Road, Park Street, William Street and Ngarongo Road. We ask kindly that this area be kept clear of vehicles and residents do not park on the road for the next couple of days. Thank you for your understanding and cooperation.

Slip on Te Waitere Road – please drive safe

Council is aware of a significant slip on Te Waitere Road. Currently the road is down to one lane with priority give way traffic control in place. Given there is poor weather forecast towards the end of the week, we encourage those needing to pass through this site to be vigilant and drive safely and to the conditions.

Traffic delays due to Rangitoto Road works

12 May 2025, 9:32 AM

 

Residents and travellers using Rangitoto Road in Te Kūiti can expect road closure delays for the next six weeks.

Construction works started in early May to upgrade sections of the road, in response to previous storm damage.

However, to safely to conduct the works, road closures are necessary.

During weekdays, a section of Rangitoto road will be closed from 9am to 2.45pm, beginning 12 May 2025 through 20 June 2025.

 

Weekday road closure details:

Duration: approx. 6 weeks

20-minute delay from 7am to 9am

Daily Road Closure Time: 9am to 2.45pm

Road closure open times: – 11am to 11.15am and 1pm to 1.15pm.

20-minute delay from 3pm to 6pm.

Location: Around 1 km each side of Tate Rd along Rangitoto Road

 

Inframax Construction Ltd were awarded the contract following a tender process.

Work includes repairing the pavement (road surface), upgrading drainage and constructing a timber retaining wall.

Both sites will be constructed concurrently so there will be a 1km section of road affected by traffic management.

The overall completion for both sites is end of June 2025.