Road works - Centennial Park area

Construction work will begin Tuesday 24 June around Centennial Park area to install concrete islands and road line marking. The roads to be marked are: Te Kūiti Road, Park Street, William Street and Ngarongo Road. We ask kindly that this area be kept clear of vehicles and residents do not park on the road for the next couple of days. Thank you for your understanding and cooperation.

Slip on Te Waitere Road – please drive safe

Council is aware of a significant slip on Te Waitere Road. Currently the road is down to one lane with priority give way traffic control in place. Given there is poor weather forecast towards the end of the week, we encourage those needing to pass through this site to be vigilant and drive safely and to the conditions.

Milestone work begins on Te Ara Tika overbridge

18 Jul 2021, 9:58 AM

An important milestone on the Te Ara Tika Bridge project kick started today with a 220 tonne large crane arriving onsite. The two main span bridge beams, complete with balustrades,  will be lifted into position onto the tops of the central columns, either side and central across the railway tracks over the next two days.

On Monday, rail protection and traction control will be set up and managed by KiwiRail (who will be monitoring the operation throughout). It will end with demobilisation of the large cranes from Carroll Street side and re-established on the Rora St side ahead of Monday’s lifting operations. The large crane will operate from the Rora St side and will lift the bridge ramps into position between the new main beams and the Rora Street landing. This is scheduled for between 8 am and 3pm.

This is a carefully planned exercise, as part of a much bigger project, with safety considerations central to that.

The installation of the remaining bridge beams is scheduled to take place during the first week of August once earthworks and surfacing of the new basketball half-court have been completed.