Road works - Centennial Park area

Construction work will begin Tuesday 24 June around Centennial Park area to install concrete islands and road line marking. The roads to be marked are: Te Kūiti Road, Park Street, William Street and Ngarongo Road. We ask kindly that this area be kept clear of vehicles and residents do not park on the road for the next couple of days. Thank you for your understanding and cooperation.

Slip on Te Waitere Road – please drive safe

Council is aware of a significant slip on Te Waitere Road. Currently the road is down to one lane with priority give way traffic control in place. Given there is poor weather forecast towards the end of the week, we encourage those needing to pass through this site to be vigilant and drive safely and to the conditions.

Large scale works for Oparure and Fullerton Roads

17 May 2024, 3:43 PM

 

Waitomo District Council’s Infrastructure Services team has recently awarded three large-scale roading projects for the district.

Commencing late May/early June, work will begin on two sections of Fullerton Road and a section of Oparure Road.

General Manager Infrastructure Services, Shyamal Ram says the winter storm in 2022 caused damage to roads across the district, with Oparure and Fullerton Roads impacted by slips.

“Due to the nature of the damage and ongoing subsidence, engineered designs were required to ensure a long-term solution.

“Along Fullerton Road, 1km from the intersection with Oparure Road had two slip sites that were reinstated as part of the emergency works recovery, however have continued to slowly slump.

“The design solution is 3m deep drainage improvements and reinforced pavement.”

For Oparure Road, the design solution is a timber retaining wall with 6m length piles, and drainage improvements.

Construction works have been awarded to Camex Civil with an estimated completion time of around three months, weather permitting.

Shyamal says he appreciates the patience of the community over the past year with the temporary measures that have been in place at the sites.

“We are pleased that construction will soon be starting, and we appreciate the understanding and patience demonstrated by those affected.”

At times construction works will be completed under stop/go traffic management which will cause minor delays.

We thank the public for their patience during this time so that the construction works can be completed safely.